PMO PROCESS
Project Management Office
Standard
Operating Procedure (SOP)
Project
Management Office at MACON ENGINEERING consists of two process groups for
managing the projects which are as follow:
A.
Core Process Group
B.
Functional Process Group
PMO |
Part-A. Core Process Group of PMO:
1. Project
Initiation
2. Project
Planning
3. Project
Budgeting (Preparation of Specification & BOQ)
4. Project
Execution
5. Project
Monitoring & Control
6. Project
Closing
1.
Project
Initiation:
A
project is initiated when a land is acquired by the Business Development (BD)
Department after the feasibility is approved by the management. Following types
of project can be initiated based on type of occupancy:
a) Residential
b) Commercial
c) Industrial
The
land is acquired and Deed of Agreement is signed by the Landowner & Sponsor
of MACON ENGINEERING (MCL). Power of Attorney has been transferred in favor of MCL
with acceptance from Landowner. Possession of the land is then taken over from
Landowner after demolishing existing structure (if any).
PMO performs the following tasks during the
process of taking the possession of the land:
a) Create
Project Identity in the ERP System.
b) Perform
the soil test (if not done earlier)
c) Check
the utility connection & report and resolve any dispute regarding the
connection in conjunction with Landowner.
d) Coordinate
for Project fencing in conjunction with the Marketing Department of MCL.
e) Coordinate
the Design Development for further course of project.
2.
Project
Planning:
Based
on the Project Completion Time as considered in the approved Project
Feasibility Report, PMO prepares the Milestone Project Schedule. Then prepares
the WBS of the project milestone deliveries in conjunction with the
Construction Manager assigned for the specific project. PMO finalizes the
mutually agreed schedule as ‘Master Schedule’ which is the reference for
executing the project in designated Time.
3.
Project
Budgeting (Preparation of Specification & BOQ):
PMO
prepares the Initial Project Specification based on the cost availed from
“Approved Feasibility Report”. The Design Team prepares the detail design based
on the Project Specification.
The
detail BOQ is prepared after the structural drawing has been developed based on
the management approved architectural drawing of the specific project.
4.
Project
Execution:
After
taking the possession of the land from the Landowner, PMO engages the
construction team for mobilization at site and start the execution of the
project.
5.
Project
Monitoring & Control:
PMO
monitors the project as per the planned schedule and keep record of the delay
(if occurs) as delay log. PMO also suggests mitigation plan to overcome the
delay in conjunction with Construction Manager.
PMO also performs following tasks during
monitoring & control phase:
a) Quality
Assurance (QA): Regularly evaluates the construction work based on the relevant
quality standards & prepares monthly QA reports.
b) Cost
Control: Regularly monitors the cost of construction work based on the approved
BOQ as per approved drawing & design. Also, reconcile the project cost in
conjunction with the Supply Chain Management (SCM) and Billing &
Coordination Team of Construction Department, so as to get the actual cost
incurred against the BOQ cost.
c) Information
Distribution: PMO makes needed information available to the project
stakeholders (including related design & drawing) in a timely manner.
d) Status
Report: PMO collects & compiles project status report to address where the
project stands a given point.
e) Progress
Report: PMO collects & compiles project progress report to address what the
project team has accomplished to date.
6.
Project
Closing:
Project closing will be initiated in following
phases:
a) Construction
completion of Client’s Floor Space (Net Carpet Area of the floor space):
Upon completion of the construction work at the floor
space of clients, PMO coordinates to give access to clients for Interior work
or provisional handover or possession handover through Customer Service
Department, depending on the status of payment schedule. CS will visit the
project with a checklist to verify the quality and status of completion.
b) Construction
completion of the project (Building Common & Floor Common area):
Upon completion of construction work at common spaces of
the project building (Building Common & Floor Common) including completion
of all features & amenities and utility services (such as Power connection,
water supply & waste water drainage, lift installation, parking facility,
etc.) PMO will arrange for a joint project visit with relevant departments
(Architects, Construction, EME, PMO and CSD) for Preliminary Acceptance
Certificate (PAC) as per the planned design & requirement and then handover
the project to the Customer Services Department for commencement of Facility
Management Services.
PMO will prepare a report (text & pictorial) of “SNAG
List” and will get a schedule for rectifying the SNAGS from Construction Team.
The project completion will be accepted upon completion of the MAJOR SNAGS with
required quality and a final acceptance certificate (FAC) will be issued to
construction team after a joint visit in conjunction with PMO & CSD with
Construction Team.
It is
to be noted that Construction Team will hand over project with the features and
amenities with a warranty period of 01 (one) year. But in case of “Construction
Fault” the construction team will be responsible for rectifying the fault/s and
cost will be borne by MCL.
If a
“Facility Management Service Team” is deployed, they have to be well briefed
about the functions, features & amenities of the project along with the “As
Built” drawing of all sectors (Architectural, Structural, EME & Plumbing).
PMO will coordinate this transition process in conjunction with the
Construction Team & Customer Service Department.
c) Construction
completion of Total Project (Ready for Handover to Common Management
Association formed among the clients including Landowner/s):
If the majority of the clients’ space along with the total
project is being handed over, Customer Service Department will approach for
formation of Common Management Association (CMA) among the clients (including
the Landowner/s) in coordination with Construction Team, PMO, Marketing Team
and Customer Experience Department. Construction Team & PMO will play
supporting role in this phase to facilitate smooth & successful completion
of the CMA formation program.
Note:
i) PMO
will not be engaged in any sort of vendor engagement and vendor management as
these are the core responsibilities of Billing & Coordination Team of
Construction Department (in case of Contractors, Labors) and Supply Chain
Management (SCM), in case of supply & installation vendors. However, PMO
will intervene in vendor coordination, if deemed necessary (in exceptional
cases where there are any bottlenecks regarding completion of works related to
vendor/contractor).
ii Project
Coordinators are responsible for the planning, execution, monitoring &
control and closing of the projects which are individually assigned by Line
Manager, PMO and will be responsible for Top Supervision of assigned projects.
Budgeting and preparation of specification & BOQ is carried out by BOQ
personnel.
Part-B.
Functional Process Group of PMO:
1. Authorizations of Payment of Utility Bills of Projects:
2. Authorizations of Requisition of Speed Money:
3. Authorizations
of Design and BOQ:
4. Authorization
of concreting & overall Quality Assurance (QA)
5. Authorizations
of Demand / Refund Adjustments for Client’s Interior Change Requests
6. Authorizations
of Waiver of Demand value and / or MCL Fee from Demand-Refund amount for client
/ land-owner request of design and specification changes
1.
Authorizations of Payment of Utility Bills of Projects:
i) Electricity Bills
ii) Titas Gas Bills
iii) WASA Bills
iv) City Corporation taxes
2.
Authorizations of Requisition of Speed Money:
i) Electricity Connection
ii) Electricity Load Conversion
iii) Electricity Pole / Line shifting
iv) Gas Connection
v) WASA Connection
vi) Road Cutting permission
vii) Ramp relation permission
viii) Sewerage Pit & drainage connection
ix) Tree cutting
x) Licensing Board NOC for Substation
xi) Fire Service NOC
3.
Authorizations
of Design and BOQ:
It is to be mentioned that all construction work/implementation
work drawing has to be endorsed by PMO. Without endorsement of PMO any
design/drawing will be treated as observation purpose and unauthorized for
execution/implementation. Similarly, BOQ & specification must be approved /
authorized from PMO for construction / execution of any project activity.
i)
Architectural Design
ii)
Structural Drawings
iii)
Material Specification and Standards
iv)
Full / Partial BOQ
4. Authorizations of Demand / Refund
Adjustments for Client’s Interior Change Requests:
i)
Additional works beyond original BOQ and
Design
ii)
Material and Specifications Change
5.
Authorizations
of Waiver of Demand value and / or MCL Fee from Demand-Refund amount for client
/ land-owner request of design and specification changes:
i)
Additional works beyond original BOQ and
Design
ii)
Material and Specifications Change
iii)
Additional Items beyond the scope of Deed /
Sales Agreement
iv)
MCL Fee from Demand Refund adjustment
I think that thanks for the valuabe information and insights you have so provided here. https://westasianetwork.com/ashford-formula-abu-dhabhi.php
ReplyDeleteThank you for giving us such great information on click here more information
ReplyDelete